Entrance project lead times and build sequence

Allow 2 to 3 weeks for new footings, pier masonry and curing, 4 to 6 weeks for made-to-measure fabrication and hot-dip galvanising, and 6 to 10 weeks overall for a complete turnkey entrance.

The right order to schedule planning checks, strip footings, triple ducting, masonry curing, laser survey and final automated handover.

Free, no obligation. One local installer prices it, not five.

  • 2–3 wksfootings, piers & curing window
  • 4–6 wkscustom fabrication & galvanising
  • 6–10 wkscomplete turnkey entrance project
  • 1–3 daysonsite hanging & commissioning
Checking boundary opening dimensions with a tape measure along the gate line

Six stages in the right sequence

Most expensive delays on Irish front entrances happen when contractors arrive out of order: tarmac laid before ducts, steel gates ordered before stone cladding narrows the gap, or resin anchors drilled into fresh green render.

  1. Stage 1: Planning or Section 5 check (0 to 4+ weeks). Confirm Class 5 exemption, verify estate covenants or secure a 4-week Section 5 or council grant before excavating.
  2. Stage 2: Excavation, footings and triple ducts (3 to 5 days). Dig strip foundations, pour rebar concrete, set underground motor drainage sumps and lay all three 50 mm conduits with draw ropes.
  3. Stage 3: Piers, splayed walls, facing and curing (1 to 2 weeks). Build concrete-cored blockwork, apply stone cladding or sand-cement render, bed pier caps and allow mortar to cure cleanly.
  4. Stage 4: Final laser measurement (1 hour on site). Once facing and ground finish levels are locked in, the gate fabricator measures exact clear gaps at bottom, middle and top.
  5. Stage 5: Workshop fabrication and duplex coating (4 to 6 weeks). Steel frames are welded, hot-dip galvanised to EN ISO 1461, fettled and powder coated (or bespoke aluminium/hardwood leaves assembled).
  6. Stage 6: Hanging, automation, Safe Electric and handover (1 to 3 days). Leaves are hung and levelled, motors and photocells tested, 4G GSM intercom paired to phones, SWA feed certified and tarmac finished.

Price my entrance

Four quick taps and our Irish price guide shows before we ask for a phone number. One local installer rings you, not five.

A country stone-pier entrance, 3.5 m to 4.8 m with new piers and wing walls, electric motors, GSM intercom and pillar lights: €9,100 to €19,200, supplied and fitted.

Step 1 of 5

What entrance setup are you pricing?

Pick the closest match. The installer checks details on site.

How the entrance guide is calculated

Figures reflect going Irish supply-and-fit rates for residential and site entrance packages. Ready-pier totals include custom gate leaves, heavy hanging ironwork and installation. New-pier and wing-wall options add excavation, reinforced strip footings, solid-cored piers and capping, with stone cladding factored in on stone-pier and wing-wall builds. Electric and full-intercom tiers add motors, IS EN 12453 safety photocells, remotes, intercom column hardware and pillar lighting allowances. Long armoured cable runs and tarmac reinstatement vary by site and are confirmed in writing after a site survey.

How to shave weeks off your project without cutting corners

  • Build piers early while keeping the workshop slot booked. Ask your installer to reserve a fabrication slot once your footing pours so galvanising turnaround does not stack onto peak spring demand.
  • Consider prefabricated craned stone piers. Lifting factory-built stone piers onto cured footings turns two weeks of wet-weather masonry into a single morning.
  • Coordinate the tarmac contractor for the final week. Leave the driveway apron at compacted 804 stone until heavy crane vans, concrete lorries and trench diggers have left the site.
  • Order special RAL finishes and stone caps upfront. Non-stock architectural powder shades and custom hand-cut limestone caps carry the longest supplier lead times.

Timeline and scheduling questions

When should I book an entrance installer during a new house build?

Get an installer to look at the site drawings before your groundworker pours front boundary footings or finishes the driveway stone base, ideally 3 to 4 months before move-in.

Why does hot-dip galvanising add time to steel entrance gates?

After custom welding is finished, bare steel leaves travel to an Irish galvanising plant for acid pickling and molten zinc dipping, then return for fettling and oven-cured powder coating.

Can my driveway be tarmacked before the gates are installed?

Yes, provided every underground duct, underground motor box and sliding concrete foundation beam is set dead flush to final tarmac height before the paver rolls in.

Does winter frost delay pier masonry and concrete footings?

Air temperatures below 3 °C halt mortar laying and concrete pouring. Autumn and spring bookings avoid both winter frost holds and summer tarmac backlogs.

Every entrance guide on this site

Checking boundary opening dimensions with a tape measure along the gate line

Lock in a site survey before groundworks start

Outline your entrance package in four taps so one local installer can map your timeline alongside your builder or groundworker.